Renfro Street Improvements - Johnson Ave to I-35W

renfro johnson to I35
Location:  Renfro Street from Johnson Avenue to Interstate 35W
Start Date:
Summer 2018
End Date: 
Spring 2019  
Purpose: Improve safety and increase capacity at the intersection
End Result: A context sensitive roadway consistent with Old Town standards, that provides for vehicular traffic while improving pedestrian mobility in the corridor as well. Medians will be added, with left turn lanes, and a major pedestrian crossing will be placed crossing Renfro Street at Main Street.
Project Cost: Approximately $1M
Funding Source: 
Street Bond Funds
- Contract with Kimley-Horn & Associates was approved in July 2017.
- As of Sept. 25 - Design work has started.
Next Steps: - Public input meeting February 22, 2018 at City Hall, 4:30 – 7:00 pm.
Closures/Detours:  To be announced