Renfro Street Improvements - Johnson Ave to I-35W

renfro johnson to I35
Location:  Renfro Street from Johnson Avenue to Interstate 35W
Approximate
Start Date:
Summer 2018
Approximate 
End Date: 
Spring 2019  
Purpose: Improve safety and increase capacity at the intersection
End Result: A context sensitive roadway consistent with Old Town standards, that provides for vehicular traffic while improving pedestrian mobility in the corridor as well. Medians will be added, with left turn lanes, and a major pedestrian crossing will be placed crossing Renfro Street at Main Street.
Project Cost: Approximately $1M
Funding Source: 
Street Bond Funds
Progress: 
- April 2018: Design work 90% complete,
- Sept. 25, 2017, Design work has started.
- Contract with Kimley-Horn & Associates was approved in July 2017.
Next Steps: - Additional Public Meeting to be held in May 2018
- Public input meeting held February 22, 2018 at City Hall
Closures/Detours:  To be announced