Widening of McNairn Road

McNairn Widening at SH174
Location:  McNairn Road at SH 174 intersection (Wilshire Blvd)
Approximate
Start Date:
To be determined
Approximate 
End Date: 
To be determined 
Purpose:
Improve the intersection of McNairn Road and SH 174 (Wilshire Blvd), widen McNairn for capacity of traffic from new commercial uses at the corner.
End Result:
The project includes:
- Widening of McNairn from the SH 174 (Wilshire Blvd) intersection for approximately 550 feet north
- Turn lanes
- Closing SH 174 (Wilshire Blvd) access road at McNairn Road
Project Cost: Approximately $350,000
Funding Source: 
Design funding is part of economic development agreement 
Progress:  Design is complete, some utilities have been relocated. 
In process of acquiring right-of-way property.
Construction will be driven by commercial development and is not currently scheduled.  
Closures/Detours:  To be determined.