1. Bufford Street at Warren Street
2. North Main Street at Renfro Street |
Approximate Start Date: |
October 2019: Construction has begun. |
Purpose: |
Provide additional parking in Old Town. |
End Result: |
The two new lots will increase parking in Old Town by 154 spaces. |
Funding Source: |
2018 CO Bonds, Water and Sewer bonds for utility work. |
Progress: |
June 2019: Bufford parking lot is now open for use. 104 total spaces are now available. Minor construction is ongoing and will be complete at the end of June. |
Closures/Detours: |
May 2019: Main Street closed North of Renfro Street during construction. |