Public Infrastructure Projects

Burleson voters approved Proposition A for $33,645,000 on the May 7, 2022 special bond election ballot. The proposition passed with 937 votes for and 844 against.  View the 2022 Bond public infrastructure projects location map.

2022 Bond Projects and Status Update

Project: Neighborhood Street Rebuilds 

Design and construction for various neighborhood streets throughout the city
$3,175,833
Project Information
Neighborhood Street Rebuilds Map
timeline graphic that shows Year 1&2 Projects complete, Year 3 in design and year 4 in planning

Project: Intelligent Traffic System

Project will provide for the design and construction of improvements to allow the city to study, control and synchronize the traffic signals throughout the city
$2,161,123
Project Information

Construction Phase

Project: SH 174/Wilshire Boulevard

Hulen Street to Wicker Hill 
Design for the expansion to six lanes
$2,330,000
Project Information

Design Phase

Project: SH 174/Wilshire Boulevard

Lakewood Drive Intersection
Design and construction of dual left-turn lanes 
$100,000
Project Information| Project was completed on November 15, 2023. 
Project Complete

Project: Alsbury Boulevard 

Hulen Street to CR 1020 
Design and construction for the extension of Hulen Street to CR 1020
$7,382,496
Project Information
Construction Phase

Project: Alsbury Boulevard 

Hulen Street to CR 914 
Design for the future widening from two to four lanes
$2,500,000
Project Information

Project: Sidewalk Program

Design and construction for various sidewalks throughout the city
$1,266,946
Project Information

a timeline that shows Year 4 projects in planning, Year 1 & 3 in Design and Year 2 projects complete

Project: Hulen Street 

  • Wilshire Boulevard 
    Design and construction for intersection improvements 
    $1,701,027
    Project Information

Project: Hulen Street 

  • Kelly Drive to Candler Drive 
    Design and construction to expand from two to four lanes
    $7,803,653
    Project Information

Project: Hillside Drive, Elk Drive & FM 731

Design and construction for intersection and sidewalk improvements
$1,036,509
Project Information
graphic of project timeline Elk Drive south section in design, Hillside, Elk (north sections) & FM 7

Bond projects scheduled for upcoming years

Project: East Renfro Street/FM 3391 

Design for the widening of the roadway
Project Information
*This project has been removed from Bond 2022 funding because TXDOT has taken on the project. 

Project: CR 1902 & CR 910 Pedestrian Mobility

Design and construction
$1,489,901
Project Information

View all of the projects